3+ Thousand Tonnes of Structural Steel Installed in Gyda Peninsula


15.03.2021

On the site of ALNG 2. Gyda Project, piling is in progress actively. Circa 21 thousand piles are fabricated, 190+ thousand meters of boreholes are drilled, 19.3+ thousand piles are sunk in the ground. Moreover, our specialists have completed installation of 3+ thousand tons of structural steel. 

Both ALNG 2. NOVARCTIC.CWP2B and ALNG 2. NOVARCTIC.CWP3B: concrete works completed (total volume exceeds 3.8 thousand cubic meters.) At the time being, builders are getting ready for routing the pipeline i.e. they are installing steel racks. 

Totally, in the Gyda Peninsula project approximately 3,000 people are working and 2,900+ units of equipment are in use.