80%+ Work Progress on Site of Nizhny Novgorod Refinery


24.03.2021

On site of the Nizhny Novgorod Refinery project, VELESSTROY is building the Offsites and PENEX Isomerisation Unit. 

Currently, the PENEX works are globally 87 % ready. On the construction site piling is finished, earth works and structural steel installation are nearly completed. Now installation and welding of process piping (90% ready), finishing (86% ready), instrumentation cabling (35% ready) and power cabling (55% ready) are our major tasks. 

Totally, work progress on the Offsites is 85%. Welding of process piping and heat tracing are in progress energetically (as of January, 285 337 Di welded.) Also, VELESSTROY builders are routing external water and sewerage pipelines and performing wiring. 

All in all, 3,500+ people are working at the facilities including contractors, engineers and service personnel.