First Phase Construction Nearing Completion at Amursky GPP


09.04.2021

Phase one works are nearing completion at Amursky Gas Processing Plant. Additional leak testing, inerting and drying of piping and commissioning works are underway. 

At phases two and three concrete works and installation of steel structures are almost finished (at both phases more than 93% of works is done). At phase two, having commenced installation and welding of piping our workers are also laying the cable lines. 

At phase four concrete casting is in full swing (48% finished) and about 27% of steel structures are installed. 

Phase five of the construction has begun: the progress for concrete and reinforced concrete structures adds up to 31%.