| 14.10.2020 |
As of today, more than 2000 t of steel structures have been installed at the Arctic LNG-2. Gydan project, with more than 170 km of wells bored and 14 800 piles installed.
Installation of cast-in-situ and prefabricated pile caps is nearing completion at the Central Control Room of the GBS LNG & SGC Plant. Pile driving works have finished at the HP Flare.
Reconstruction of the onshore facilities of the operating Utrenniy LNG & SGC berth has started.
Construction of five dorms, one canteen and a bathing zone is in progress. 2 dorms have been constructed and are already in use.
At the moment, the project employs more than 1800 people. Soon, the number of personnel is expected to increase by 600 more.