| 16.11.2020 |
At the Nizhny Novgorod Refinery Velesstroy has two construction areas:
• At the PENEX Isomerization Unit construction site we have completed 85% of the welding and installation activities and have commenced the electrical works - installation of the power and instrumentation cables; simultaneously, we are installing the external water supply and sewage lines and performing the site improvements.
• At the Petroleum Residue Recycling Complex Offsite Facilities, the welding activities are 69% done.
The construction is schedulled to end in 2021.