| 12.10.2020 |
Amursky Gas Processing Plant construction project has activities of all work phases performed in parallel. As of today, almost all structural and concrete works have been finished and cable works (89.1%), piping installation and welding (79%) and pipeline testing and insulation works are underway at the first phase.
At the second phase, concrete and installation works are almost over (98.7%) and cable works are in progress (13.2%). At the third phase, concrete works are 91.7% finished and 63.8% of steel structures has been installed.
For the fourth and fifth phases, we have finished installing the piling and at the moment foundation concrete casting is underway.