Second stage construction begins at Sakhalin Booster Compressor Station


04.05.2021

Earthworks, installation of steel structures and sandwich panels, foundation casting are almost finished. Equipment installation, waterproofing and backfilling of foundations are in full swing. 

Simultaneously, we are welding underground and aboveground pipelines - this required mobilizing additional welding teams. Having installed the second section of the Flare Unit, our colleagues are also preparing for the installation of the Flare's last section. 

At the same time, Velesstroy team is launching the second stage of construction. We will be performing finishing works inside the buildings, pulling cables over the racks, fireproofing the transformer substation.